1.
Liquidated Damages. Cuesport
Properties, LLC, sold a condominium in Anne Arundel County, Maryland, to
Critical Developments, LLC. As part of the sale, Cuesport agreed to build a
wall between Critical Developments unit and an adjacent unit within thirty
days of closing. If Cuesport failed to do so, it was to pay $126 per day until
completion. This was an estimate of the amount of rent that Critical
Developments would lose until the wall was finished and the unit could be
rented. Actual damages were otherwise difficult to estimate at the time of the
contract. The wall was built on time,
1.
Liquidated Damages. Cuesport
Properties, LLC, sold a condominium in Anne Arundel County, Maryland, to
Critical Developments, LLC. As part of the sale, Cuesport agreed to build a
wall between Critical Developments unit and an adjacent unit within thirty
days of closing. If Cuesport failed to do so, it was to pay $126 per day until
completion. This was an estimate of the amount of rent that Critical
Developments would lose until the wall was finished and the unit could be
rented. Actual damages were otherwise difficult to estimate at the time of the
contract. The wall was built on time, but without a county permit, and it did
not comply with the county building code. Critical Developments did not modify
the wall to comply with the code until 260 days after the date of the contract deadline
for completion of the wall. Does Cuesport have to pay Critical Developments
$126 for each of the 260 days? Explain. [Cuesport Properties, LLC v.
Critical Developments, LLC, 209 Md.App. 607, 61 A.3d 91 (2013)] (See Damages.)
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more